Water Improvement Benefit Area No. 1 – May 1, 2024 Update
The status provided to the Town of Clarkson by its engineers, MRB Group, is as follows:
1. All easements have been obtained and filed by Attorney Olson.
2. All permits and approvals have been obtained.
3. All paperwork to bid the project was provided to USDA RD as of 4/23/24. Once USDA RD reviews the documents and finds them satisfactory, they will give permission to bid the project.
Assuming USDA RD has no problems with the documents submitted and gives permission to bid in the next couple weeks, the anticipated schedule will be as follows:
1. Advertise for bids mid-May
2. Open bids mid-June
3. Start of construction end of July
4. Construction completed and cleaned up summer 2025
Please feel free to contact Scott Mattison, Engineer @MRB Group, 585.340.3661 or Clarkson Town Hall, 585.637.1130 with your questions.